The laying of low-voltage track is divided into the following three steps:
1. Track foundation laying. Perfect Handling Equipment provides track foundation drawings for the tonnage of customers purchasing transfer carts. The customer asks the civil engineering staff to carry out the construction. During the civil construction, the anchor bolts should be pre-embedded into the foundation in advance according to the requirements of the drawings.
2. After the foundation is completed, the ground is leveled first, and then the insulating felt is laid on the ground, the track is placed on the insulating felt, and then the insulating pressing plate is fixed and the conductive copper bar is welded. After all these tasks are completed, in order to ensure the insulation of the track, a mixture of asphalt and stones needs to be stacked on both sides of the track, compacted and flattened.
3. Arrange commercial concrete for the second pouring of the track, and the second pouring and paving work will be completed by the customer. Note that the middle of the two tracks is slightly higher than the two sides